+7 / 7187 / 278-543

Restoring repair of power unit 500 MW st. № 1 «Ekibastuz GRES-1 named after Bulat Nurzhanov» LLP

According to the general contract agreement No. 007-718 dated 06.11.12 “Restoration repair of power unit No. 1” by the specialists of our company, work continues on the restoration of power unit No. 1. The contract is valid until 31.04.2024.

The projected completion date of this project is 31.12.2023..
Within the framework of contractual obligations, the following scope of work is planned for implementation in 2022:

– Installation of the turbine unit To-500-240- 3M;

– Installation of the main boiler equipment, installation of the main high-pressure pipelines;

– Installation of electrical equipment and instrumentation;

– Installation of building structures and auxiliary pipelines.

Back

Our News

31 July 2024

Тeambuilding

Switch to mobile version